Delivering projects in Riyadh
Off-plan projects in Riyadh are licensed through Wafi, which REGA oversees, and buyer payments sit in a project escrow account that releases funds as construction advances. That puts the progress figure at the centre of the developer's cash plan, so RealMake keeps approved progress, inspection records and photos together by milestone. Milestone demands sent to buyers apply 15% VAT where due and carry the Arabic fields ZATCA requires. Developers whose VAT-subject revenue passed SAR 187,500 in any year from 2022 to 2025 fall in FATOORA wave 25 and must integrate by 1 February 2027. The 5% Real Estate Transaction Tax applies on sales.